Building 2 pump room required the replacements of an existing transformer and associated power distribution to the Building 2 Pump Room on the NIST Campus.  The scope of work included removing an existing 500 KVA transformer and replacing it with a 750 KVA transformer, adding an additional 3” underground conduit next to existing conduits, removing and replacing conductors in exiting conduits and adding conductors for new conduit.  Also removing and replacing a 600A panelboard with a 1000A panelboard.
Project Name: Nist Building 2 Pump Room
Location: Nist Boulder, Co
Electrical Value: $182,000.00